Construction/Installation Time Line
PRE-CONSTRUCTION STAGE
Sales Agreement, Builder Meeting, Design Studio Appointment, Lender Approval, Permits, Excavation of Site (10-30 days)
STAGE 1 - Permits to beginning of footings (14-21 days)
- Exterior Doors
- House Wrap
- Jetted Tub
- Laundry Sink
- Additional OSB Sheets
- Kitchen Cabinets
- Sinks
- Corian and Countertops
STAGE 2 - Footings to slab pour (10-15 days)
- All Electrical
- HVAC
- Security System
- All Plumbing
STAGE 3 - Framing (5-15 days)
- Door Hinges
- All Trim & Crown Molding
STAGE 4 - Rough ins to beginning drywall (8-10 days)
- Door Hardware (Interior/Exterior knobs and handles)
- Hardwood Flooring
- Laminate Flooring
- Tile Flooring
- Vinyl Flooring
STAGE 5 - Drywall (5-15 days)
- Appliances
- Tile Backsplash
- Faucets and Fixtures
- Concrete Pad and Patio
- Carpet and Pad
- Deck (Per home site requirements)
- Insulation
- Paint
- Lighting
- Toilets
- Shelving
STAGE 6 - Cabinet installation to paint finish (7-15 days)
- Fencing
- Landscaping (Sod and Sprinklers)
STAGE 7 - Flooring to finish work (15-20 days)
- NO CHANGES ALLOWED-Less than 45 days to close
STAGE 8 - Orientation to close (14 days)
- 2 Weeks to address punch list items to close
***All time estimates depend on weather factors *** All days are working days ***